Why Tanzania · corridor infrastructure

Ports, rail & logistics: is the corridor becoming an operating system?

The gateway is handling more cargo while new rail and dry-port links enter operation. The evidence is useful only when calendar years, fiscal years, construction progress and actual throughput remain visibly separate.

Tracked to the official source's own cadence, not presented as a streaming feed. Every chart keeps its observation date, unit and scope attached.

Evidence set checked .

Cadence: Annual budget speech, supplemented by official project notices

Official source

As at · Source: Ministry of Transport

Dar port cargo

27.76m tonnes

Ministry-reported fiscal-year cargo, versus 16.27m tonnes in FY2020/21. Period: FY2024/25.

Official source

As at · Source: Ministry of Transport

Dar port cargo

25.07m tonnes

Ministry-reported nine-month value; not annualised. Period: 2025-07 to 2026-03.

Official source

As at · Source: Ministry of Transport

SGR freight

102,452 tonnes

Ministry-reported freight since SGR freight operations began. Period: 2025-07 to 2026-03.

Official source

As at · Source: Ministry of Transport

Kwala dry-port containers

14,460

Containers handled through the reported period. Period: through 2026-03.

Official source

As at · Source: Ministry of Transport

How has the official all-port cargo total changed?

All-port cargo throughput

As at 31 Dec 2023 · Source: Tanzania Ports Authority. Exact values and method remain in the static evidence table below.

How much freight did the two rail networks report?

Rail freight by network

As at 31 Dec 2024 · Source: National Bureau of Statistics Tanzania. Exact values and method remain in the static evidence table below.

How did the published vessel-time measures move?

Dar container-terminal vessel time

As at 31 Dec 2023 · Source: Tanzania Ports Authority. Exact values and method remain in the static evidence table below.

Official detailed history · 2023

1,023,177 TEUs

Total TPA container throughput. A separate Dar-specific 2023 value is withheld because two tables in the bulletin disagree.

Official source

As at · Source: Tanzania Ports Authority

Withheld, not averaged

Two unresolved official-source conflicts

  • TRC and TAZARA rail freight, 2024: Withheld pending reconciliation: official NBS publications report different 2024 values.
  • Dar es Salaam port container throughput, 2023: Withheld because two tables in the TPA bulletin disagree.

From blueprint to operation · Ministry-reported

Corridor project status

Progress percentages are physical-progress reports, not capacity or throughput. Operating status is shown separately from construction.

  1. operating

    SGR freight and Kwala dry port

    Official freight operations began in July 2025.

    Official source

    As at · Source: Ministry of Transport

  2. under construction

    SGR port connection

    99.09%

    Ministry-reported physical progress.

    Official source

    As at · Source: Ministry of Transport

  3. under construction

    Mwanza to Isaka SGR

    68.77%

    Ministry-reported physical progress.

    Official source

    As at · Source: Ministry of Transport

  4. under construction

    Tabora to Kigoma SGR

    9.59%

    Ministry-reported physical progress.

    Official source

    As at · Source: Ministry of Transport

  5. under construction

    Kurasini Port Extension Phase 1

    92%

    Ministry-reported physical progress.

    Official source

    As at · Source: Ministry of Transport

  6. early works

    TAZARA revitalisation

    Revitalisation launched after the September 2025 concession; survey and design work remained under way.

    Official source

    As at · Source: Ministry of Transport

What the public record supports

Reading the evidence without outrunning it

Gateway

Port throughput expanded in the detailed record.

All-port cargo rose from 16.80 million tonnes in 2018 to 26.48 million in 2023. Current Ministry fiscal-period KPIs are kept separate rather than spliced into that series.

Rail

New capacity must become observed freight.

SGR freight operations and Kwala now have reported operating volumes. Design capacity and construction percentages remain reference fields, not realised throughput.

Control

Conflicting official values stay out.

The 2024 rail point and one Dar container figure remain withheld. Preserving the gap is more informative than manufacturing a false consensus.

Freshness contract

What updates, and when

“Latest” means the newest verified observation the named authority has published. A source check never advances an observation date.

Official annual bulletin; no newer detailed bulletin located

Detailed port throughput and efficiency

All-TPA cargo, containers and Dar es Salaam container-terminal performance.

Official source

As at · Source: Tanzania Ports Authority

Annual budget speech and official event updates

Port and rail operating KPIs

Ministry-reported port and rail operating KPIs plus project status.

Official source

As at · Source: Ministry of Transport

Not public until dated retrieval and archive validation are stable

Daily shipping-list pilot

All-TPA cargo, containers and Dar es Salaam container-terminal performance.

Official source

As at · Source: Tanzania Ports Authority